PROJECT MANAGEMENT STUDY AND REFERENCES
(These are notes from my study (credits to PMBOK, University of Washington, College of Global Economics and various sites listed at the external links section). It has been very useful for PMP certification preparation and reference for PMs.
Project management is a temporary endeavor undertaken to create a unique product or service. Project management is the application of knowledge, skills, tools and techniques to a broad range of activities in order to meet the requirements of the particular project.
Programs: Programs are generally larger in scope than projects and do not have a definitive end.
Tasks: Tasks can be secondary and support projects, or they can exist as part of ongoing operations. Tasks are often completed by an individual and may not be complex or need to be integrated with other tasks.
PROJECT
LIFE CYCLE
(Project management Process Groups) |
-
INITIATION
-
PLANNING
-
EXECUTION
-
CONTROL
-
CLOSE-OUT
|
PROJECT MANAGEMENT KNOWLEDGE AREAS
Inputs:
documents or documentable items that will be acted upon
Tools/techniques; Mechanism applied to the Inputs to create
Outputs
Outputs;
Documents or documentable items that are a result of the process |
- Integration
Project plan Development
Project Plan Execution
Integrated Change Control
- Scope
Initiation
Scope Planning
Scope Definition
Scope Verification
Scope Change Control
- Time
Activity Definition
Activity Sequencing
Activity Duration Estimating
Schedule Development
Schedule Control
- Cost
Resource planning
Cost estimating
Cost budgeting
Cost control
- Risk
Risk management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring Control
- Quality
Qulity Planning
Quality Assurance
Quality Control
- Human Resource
Organizational Planning
Staff Acquisition
Team Development
- Communications
Communications Planning
Information Distribution
Performance Reporting
Administrative Closure
- procurement
Procurement Planning
Solicitation Planning
Solicitation
Source Selection
Contract Administration
Contract Close-out
|
PROCESSES & Relationships |
Authority=
right to act
Responsibility=Obligation
to act
Accountibility=being
liable for actions
Power =
ability to act without necessarily having
a right to act
The parity principle states that authority and
responsibility go hand in hand to effectively perform a task |
ORGANIZATION TYPES;
|
Theory of
Motivation:
|
Interpersonal aspects
|
LEADERSHIP, STYLES,
THEORIES, ROLES, FUNCTION |
PROJECT
PLANNING HIERARCHY
Project definition
Organizational structure
Objectives.
Team member roles
The
project manager role
Milestones
Scope |
Project
Interfaces; Organizational, Technical and Interpersonal .
They occur simultaneously |
QUESTIONS AND TESTS |
Terminology, Vocabulary |
Project Closing |
Additional Study
Project initiation, scope mng, implementation, Incubation,
Close, WBS |
|
Formulas |
Operating Profit;
Amount of Money earned= Revenue- (direct+indirect costs)
EXPECTED VALUE
=Probability * Impact
PRESENT VALUE
=FV/(1+r)n
EARNED
VALUE MANAGEMENT SYSTEM EVMS EV brief descriptions and
Formulas
PERT Weighted Average
(expected time)
Sandard Deviation Variance
|
SPC Statistical Process
Control
|
MEDIAN
= (TOTAL OF THE TWO CENTER DATA
DIVIDED BY TWO)
MODE = (MOST REPEATED TWO DATA)
MEAN =(TOTALS OF VALUE DIVIDED BY
TOTAL DATA ITEM)
RANGE = (LARGEST VALUE-SMALLEST
VALUE)
MAD (Mean Absolute Deviation) =
(DATA + MEAN FOR EACH, TOTAL / BY TOTAL DATA ITEM)
VARIANCE=(DATA + MEAN FOR EACH,
TOTALS OF SQ2 / BY TOTAL DATA ITEM)
SD (Standard Deviation) = ( SQ2 OF
VARIANCE DATA)
Pareto Diagram 20-80 rule. data arranged in
descending order of importance.
|
PROJECT TIME MANAGEMENT
|
ADM
Arrow Diagramming Method: PERT and CPM Focuses on Float
duration to determine which activities have the leaat
scheduling flexibility
PERT
Program Evaluation and Review technique; Emphasis on
meeting schedules with flexibility on cost, Pessimistic,
Most likely, Optimistic. Event oriented, uses
Dummy, Activity On Arrow (AOA), Finish
to start logical relationship, time estimates appear on
arrow
Critical
Path Method (CPM) ; Emphasis on cost
and leaving the schedule flexible, one time estimate
per activity, activity oriented, uses dummy, (AOA) Activity
On Arrow, time estimates appear on Arrow
Precedence
Diagram Method (PDM) ; Activity
Oriented, Represents improvement to PERT and CPM by
adding lag relationship to activities, (Start to Start,
Start to FInish, FInish to Start, Finish to finish) Arrow
indicates dependency, Activity On Node
(AON), No Dummy
GERT
A network Diagram drawing method that allows loops between
tasks. It is method of Sequencing
Barchart
(GANTT) Effective progress reporting tool; no logical
relationship shown between activities
Graphical Evaluation and
Review techniques are similar to PERT but have the
distinct advantages of allowing for looping, branching, and
multiple project end results |
ESTIMATES: Definitive (+- 5%)
Capital Cost (+- 10% – 15%)
Appropriation ( +- 15% – 25%)
Feasibility (+_ 25% – 35 %)
Order of Magnitude ( > +- 35%)
Benefits are not profits, Benefits = Revenues/Payback
Benefit Cost ratio (BCO)=Benefits(or Payback or Revenue)/Costs
Selecet Project with HIGHER BCR, BCR of >1 means benefit is greater than cost,
so it is good.
The smallest range estimate is the least risky
ANALOGOUS Estimating; Top down, based on similiar
projects;Expert Judgment
Bottom Up Estimating ; Detailed cost estimates of work
packages Best overall quality of estimating
Parametric Estimating; Relies on knowledge of Mathematical
relationships. Measured in $/unit.(duration prediction is based
on past average) |
Key Network
Scheduling Principles
Earliest
start:
The
earliest an activity can begin based on its relationship to its
predecessor’s duration.
Latest
start:
The
latest an activity can begin and still satisfy requirements set
forth by successor activities.
Earliest
finish:
Based on
the relationship with a predecessor, the earliest an activity
can be completed.
Latest
finish:
Based on
the relationship with a successor, the latest an activity can
be completed.
Float time:
The
amount of free time (slack time) an activity has without
impacting due date of the project.
FREE FLOAT same but applies to any immediatly folloving
activities not the Project
Forward
pass:
A technique that works forwards, starting with the first node
in the network, to determine earliest start and finish times.
Backward
pass:
A
technique that works backwards, starting with the last node in
the network, to determine latest start and finish times.
|
Programs
and Tasks Versus Projects
Programs are generally larger in scope than projects and do
not have a definitive end
Tasks
can be secondary and support projects, or they can exist as
part of ongoing operations. Tasks are often completed by an
individual and may not be complex or need to be integrated with
other tasks
Project
is a temporary endeavor that has a beginning, a middle, and
an end, only done once
|
The
primary distinction
between
planning and control
is that
you normally use
control after activities have begun.
Planning is not effective without control, and control cannot
take place without a plan
SEE CONTROL
|
Deliverables represent the need-satisfying outputs of a
project. Deliverables are significant because of the role they
play in determining if your project succeeds or fails
Stakeholders
are those who enable the existence of a project.
Indirect stakeholders
are those who are unknowingly or unwillingly affected by your
project
|
Brainwriting
Brainwriting is a means of increasing group participation. It
is especially useful when one or more members tend to
monopolize idea generation or when people are reluctant to
participate
Brainstorming
Brainstorming is a way to spontaneously produce many ideas in a
short period of time |
“Project Crashing“, the reduction of
project duration by applying additional resources to labor
intensive activities
|
Parametric modeling is reliable when
a) the
historical information used to develop the model was accurate
b) the parameters used in the model are readily
quantifiable
c) the model is scalable (i.e. it works
well for a large project as for a very small one
|
|
|